This nine-story ramp expanion project at the MSP/STP International Airport consists of 8,500 stalls, occupies three million square feet, and has four new 100’ diameter helices. The lower three levels provide service for rental cars including quick turnaround facilities. Under Spline Road there is a 1,200 foot tunnel for the automatic people mover.
Sixty
bridges were built connecting the
new and existing ramps. An 80,000 square-foot, nine-story core building
connects a tunnel, a new entrance, the parking levels, the exit roads,
and the plazas. The project was designed and built in multiple bid
packages.
The existing parking ramps were in service during construction, which required phasing of work at ingress, egress, and access lanes. Five snow melters were installed on the roof. An existing one-story rental car deck was demolished to make room for new construction.
Construction Period 1997 - 2001Planning, functional design, site logistics, structural design, and construction observation (with site offices).