This
2-building, 367,600
sf luxury condominium with underground parking is located along
Shoreline drive
next to the shores of Lake Minnetonka in Spring Park and features 120
residential
units and
262 parking stalls.
PAI
provided the
structural design engineering and construction documents for both the 3
level and 5 level
structures
constructed of post-tensioned concrete floors, slab-on-grade foundation
and
concrete columns with steel beams and light gauge metal framing
featuring brick
veneer, stucco and a metal paneled exterior.
This
project used a
design-build delivery method instead of the traditional
design-bid-build
construction process.
As
integral members
of the design-build team, PAI engineers prepared structural plans,
structural calculations and drawings along with project
specifications
for construction.
Project
Drawings were prepared in AutoCADD.
Construction
Cost
$42
million Construction Period
June 2005 - October
2006